Heather Lucy analyses the lessons that can be learnt from a judgment in an ultra-high-net-worth case as to interim applications more generally The preparation of a separate budget for an interim application adds an additional element of costs and can cause concern that the applicant is effectively benchmarking their needs, which can then impact on …
Cases Referenced
Cases in bold have further reading - click to view related articles.
- Collardeau-Fuchs v Fuchs [2022] EWFC 6
- CW v CH (MFPA 1984 Part III: Interim Applications) [2022] EWFC B1
- F v F (Maintenance Pending Suit) (1983) 4 FLR 382
- Moore v Moore [2009] EWCA Civ 1427
- Rattan v Kuwad [2021] EWCA Civ 1
- Villiers v Villiers [2020] UKSC 30